Capacity planning in a 10–20 person agency isn't a quarterly exercise. It's a 30-minute weekly routine that answers three questions: is anyone overloaded in the next two weeks, who has room in the next six, and can we take the work sales is about to close?
What you need before the first meeting
- Real working hours per person. Not “40 for everyone”: a four-day week, a short Friday or a part-time producer changes the answer. Record hours per weekday.
- Known unavailable time. Holidays, conferences, off-sites, parental leave dates you've been told about. You only need dates and hours — not reasons.
- Every active project with a status. Confirmed if signed or committed; tentative if it's a proposal, pitch or “probably in January”. Give tentative work a rough probability.
- Allocations as ranges. “Ben, Website rebuild, 6 hours a day, 16 Nov – 24 Dec” is easier to keep current than six weekly numbers.
The weekly routine (30 minutes, same day each week)
- Refresh availability (3 min). Add any new time off and check start or end dates for people joining or leaving. Capacity changes first, so everything after is measured against the right number.
- Fix the next two weeks in the confirmed lens (10 min). Look only at signed work. Anyone marked over capacity here has a problem now. Resolve it: move a task's dates, split an allocation, hand part of it to someone with the same skill, or agree a later delivery with the client.
- Look 3–6 weeks out for bench time (5 min). Who drops below, say, 60 % planned? That's capacity sales can promise, internal work can use, or a sign a project ended earlier than planned.
- Add the pipeline in the tentative lens (7 min). Switch to confirmed + tentative. Where does overload appear if the likely deals land? Those are the people and weeks to protect before saying yes — or the reason to quote a later start date.
- Decide, then tell people (5 min). Write down the two or three changes you agreed, update the plan, and make sure everyone affected sees their next four weeks.
Keep the meeting about the next six weeks. Weeks 7–12 are for spotting trends, not for re-planning every day.
Pick a target, not 100 %
Planning everyone to 100 % of their hours guarantees overruns: estimates slip, clients ask for “one small change”, and internal work (reviews, hiring, pitches) still has to happen. A practical approach:
- Set a target planned load per role — many agencies aim for roughly 75–85 % for delivery roles and lower for leads and producers, who spend time on coordination. These are rules of thumb; adjust them to your own history.
- Treat the gap between the target and 100 % as a buffer, not as spare capacity to sell.
- Plan new work into someone's buffer only knowingly, for a few weeks at most.
The utilization guide covers how to measure this and how planned load differs from billable utilization.
Read overload by day as well as by week
A week can look fine in total — 38 of 40 hours — while Monday has 10 hours booked and Friday 4. If two projects both expect someone on the same day, the weekly sum hides the clash. Check days for the next two weeks; use weeks for everything further out.
Handle tentative work deliberately
- Count it in full when the deal is big or close. If a pitch would take two designers for six weeks, plan as if it lands — at 100 % — and see what breaks.
- Weight it by probability when there are many small deals. Across ten small proposals at 30–50 %, the expected load is a more useful planning number than the worst case.
- Try big changes as a what-if. Copy the plan, staff the new project, move what it displaces, and compare before committing.
Common pitfalls
- Planning people instead of work. “Ana is on Northwind” hides how many hours. Allocate hours or a percentage, and let the totals show the truth.
- Forgetting non-project time. Account management, internal design system work and hiring are real allocations. Create an internal project for them.
- Re-planning silently. If you move someone's work, tell them. A read-only staff view helps, but a sentence in your team chat helps more.
- Treating the plan as a promise. A capacity plan is a forecast. It's there to start the right conversation early, not to measure people.
A one-page checklist
- ☐ Time off and start/end dates updated
- ☐ No confirmed overload in the next 2 weeks
- ☐ Bench time in weeks 3–6 noted and shared with sales
- ☐ Pipeline checked in the tentative lens; risky weeks flagged
- ☐ Changes written down and people told