Utilization is the share of someone's available time that goes to work you planned (forecast) or did (actual). It is the most quoted and most misused number in agency operations. Here is how to calculate it, what a healthy range looks like, and how to forecast it without timesheets.
The basic formula
utilization = hours on work ÷ available hours × 100 %
Both halves need a definition before the number means anything:
- Available hours are contracted working hours minus time someone is unavailable (holidays, leave, conferences). A person on 8, 8, 8, 8 and 6 hours has 38 available hours in a normal week and 30 in a week with Wednesday off.
- Hours on work depend on what you are measuring: all project work, or only billable client work.
Billable utilization vs planned load
| Measure | Numerator | Answers |
|---|---|---|
| Billable utilization (actual) | Billable hours logged | How much paid work did we do? Needs time tracking. |
| Planned load (forecast) | All hours allocated to projects | How full is each person in the coming weeks? |
| Planned billable load (forecast) | Hours allocated to client projects only | How much of next month is already sold? |
Capacity planning works with the forecasts. Actuals belong to time tracking, which is a different job and a different tool — CapacityKit deliberately doesn't do it.
A worked example
Chloe works 7.5 hours a day, five days a week: 37.5 available hours. Next week she has 30 hours on two client projects and 3 hours on an internal design-system project.
- Planned load: (30 + 3) ÷ 37.5 = 88 %
- Planned billable load: 30 ÷ 37.5 = 80 %
If Chloe takes Friday off, available hours drop to 30. The same plan is now 33 ÷ 30 = 110 % — overloaded by 3 hours, before anyone changed a single allocation. That is why availability belongs in the calculation.
What is a healthy range?
There is no universal standard. Common rules of thumb in small agencies are:
- Delivery roles (designers, developers, copywriters): around 70–85 % planned load. Higher leaves no room for estimate slips and reviews.
- Leads and producers: lower, often 50–70 %, because coordination, reviews and client calls rarely show up as project hours.
- Owners and account people: whatever is left after sales, hiring and running the business — plan it explicitly rather than assuming it.
Treat these as starting points. Your own history — how often weeks above 85 % turned into late nights — is a better guide.
Forecasting utilization for the next 12 weeks
- Start from available hours per day, not per week, so part-time patterns and single days off are counted correctly.
- Add confirmed allocations. This is your floor: the load you have promised.
- Add tentative work twice. Once at 100 % (the risk if everything lands) and once weighted by probability (the expected load). The truth is usually between them.
- Read it per person and per team. A team at 75 % can still have two people at 120 % and three on the bench.
- Look at the shape, not just the number. A forecast that is 90 % for the next two weeks and 40 % in week six tells sales exactly when to start new work.
Pitfalls
- Using contracted hours as available hours. Ignoring holidays makes everyone look under-used in summer and December.
- Averaging away overload. Weekly or team averages hide individual overloaded days. Check both.
- Turning utilization into a performance score. It measures the plan, not the person. A low number usually means the pipeline is thin, not that someone is idle by choice.
- Mixing tentative and confirmed work. Keep them separate so you can see both the floor and the risk.
CapacityKit shows planned load per person with confirmed work only and with tentative work added, for every week of the next 12. Explore the sample plan or create a free workspace.